One Earth Sequestration is developing a proposed carbon dioxide pipeline connecting the One Earth Energy facility near Gibson City with one planned injection well, OES No. 1, in McLean County. No ICC Certificate of Authority application has been filed, and the proposed route has not been approved by the Illinois Commerce Commission.
This page provides current project information and will be updated as route maps, public meeting details, and filing milestones become available.
1. Project Status at a Glance
Search ICC Pipeline Information
-
Not yet filed.
-
Prefiling public outreach and preparation of the ICC application.
-
The proposed pipeline requires federal, state, and local permits, approvals, registrations, and agency consultations. The following list identifies the approvals currently anticipated for construction and operation of the pipeline. Final applicability may depend on the approved route, final engineering, construction methods, and agency determinations. Status information will be updated as the project advances.
• Illinois Commerce Commission – Certificate of Authority
Status: Not yet filed. OES is completing prefiling activities and preparing the application for anticipated filing in Fall 2026.• Pipeline and Hazardous Materials Safety Administration – Operator Identification Number and required pipeline filings and notifications
Status: Operator Identification Number 40452 was received on September 22, 2022. Additional required filings and notifications will be completed before construction or operation, as applicable.• U.S. Army Corps of Engineers – Clean Water Act Section 404 and Rivers and Harbors Act Sections 10 and 408 authorizations, if applicable
Status: Applicability is being confirmed for the current pipeline route and construction plan. Any required applications and authorizations will be completed before construction.• U.S. Fish and Wildlife Service – Endangered Species Act Section 7 and related wildlife consultations
Status: Environmental review and federal agency consultation are ongoing.• Illinois Department of Natural Resources – Illinois Endangered Species Protection Act and EcoCAT consultation
Status: Consultation has been completed previously and will be updated or supplemented if required for the final route and construction plan.• Illinois Environmental Protection Agency – General NPDES Permit for Stormwater Discharges from Construction Site Activities (ILR10)
Status: Anticipated before construction begins.• Illinois Environmental Protection Agency – General NPDES Permit for Hydrostatic Testing of Pipelines and Tanks (ILG67)
Status: Anticipated before pipeline hydrostatic testing.• Illinois State Historic Preservation Office – Historic and cultural-resource review
Status: Cultural-resource investigations and agency consultation are ongoing.• Illinois Department of Agriculture – Agricultural Impact Mitigation Agreement
Status: An Agricultural Impact Mitigation Agreement became effective on July 27, 2023. Its application to the current project configuration will be confirmed before construction.• Ford County – Road-crossing, access, and other applicable county approvals
Status: To be obtained before construction, as applicable.• Ford County – Building, zoning, or planning approvals
Status: Applicability will be confirmed during final engineering.• McLean County – Road-crossing, access, and other applicable county approvals
Status: To be obtained before construction, as applicable.• McLean County – Building, zoning, or planning approvals
Status: Applicability will be confirmed during final engineering.Additional utility, drainage, or infrastructure-crossing approvals will be obtained if required by final engineering. No municipal permits are presently anticipated because the proposed pipeline route does not cross or traverse any incorporated municipality.
-
One proposed 8-inch carbon dioxide pipeline connecting the One Earth Energy facility with one planned injection well, OES No. 1
-
A downloadable description of the proposed pipeline project is provided here
-
The proposed pipeline route is located in Ford and McLean Counties, Illinois. It does not cross or traverse any incorporated municipality.
-
Four prefiling public meetings are scheduled. Meetings will be held at 10:30 a.m. and 5:30 p.m. on October 7, 2026, at the Countryside Campground Event Center in Gibson City and on October 15, 2026, at the McLean County Fairgrounds Mini-Expo Building in Bloomington. Complete meeting and accessibility information is provided in Section 2.
-
Public route maps, GIS-compatible route files, county parcel-mapping resources, and instructions for reviewing property proximity are available in Section 4.
-
September 4, 2026.
2. Public Meetings
Confirmed meeting dates, times, locations, and accessibility information are provided below. Downloadable county public meeting notices are available in Section 3. Meeting materials will be posted as they become available.
-
Date: Wednesday, October 7, 2026
Time: 10:30 a.m.
Location: Countryside Campground Event Center
Address: 403 E 200 N Road, Gibson City, Illinois 60936
Meeting materials: To be posted
-
Date: Wednesday, October 7, 2026
Time: 5:30 p.m.
Location: Countryside Campground Event Center
Address: 403 E 200 N Road, Gibson City, Illinois 60936
Meeting materials: To be posted
-
Date: Thursday, October 15, 2026
Time: 10:30 a.m.
Location: McLean County Fairgrounds Mini-Expo Building
Address: 1106 Interstate Drive, Bloomington, Illinois 61705
Meeting materials: To be posted
-
Date: Thursday, October 15, 2026
Time: 5:30 p.m.
Location: McLean County Fairgrounds Mini-Expo Building
Address: 1106 Interstate Drive, Bloomington, Illinois 61705
Meeting materials: To be posted
-
Each meeting location will be accessible to persons with disabilities. Information for requesting reasonable accommodations or interpreter assistance will be included in the applicable meeting notice.
-
Comments may be submitted at a public meeting or through the methods provided in the Questions and Comments section of this page.
3. Landowner Notices and PUBLIC MEETING Documents
Public notices, meeting materials, and related documents will be posted in this section as they become available.
-
The landowner notice form and accompanying project information will be posted here when finalized and approved for distribution.
-
A downloadable copy of the final Ford County Notice of Filing and Public Meetings is available below.
-
A downloadable copy of the final McLean County Notice of Filing and Public Meetings is available below.
-
A copy of the newspaper publication notice will be posted here when available.
-
Downloadable copies of presentation materials, posters, and handouts will be posted here as they become available.
-
A written summary or transcript of questions and comments raised at each public meeting will be posted here, together with responses when available.
-
Following the final prefiling public meeting, One Earth Sequestration will post a consolidated written summary of public questions and comments, responses, and any project modifications considered.
-
A machine-readable table identifying property owners who receive the required project notices will be posted after the notices are issued and the appropriate legal and privacy review is completed.
4. Planned Route Maps
The maps and downloadable files below show the currently planned carbon dioxide pipeline route and associated project facilities. The proposed route has not been approved by the Illinois Commerce Commission and may be refined during engineering and regulatory review.
Route Description
The currently planned approximately 5.4-mile, 8-inch carbon dioxide pipeline would begin at the One Earth Energy ethanol facility on the western edge of Gibson City in Drummer Township (T. 23-24 N., R. 7 E.). From the facility, the route would proceed west approximately 2.55 miles, crossing N 300 E Road, N 200 E Road, and N 100 E Road.
At approximately mile 2.55, the route would turn northwest and continue approximately 0.9 mile to the Ford-McLean County line at N 4200 East Road. In Cheney’s Grove Township (T. 23 N., R. 6 E.), the route would continue northwest approximately 0.75 mile to the south side of E 1400 N Road.
The route would then proceed west approximately 0.15 mile before crossing north over E 1400 N Road for approximately 200 feet to the Mainline Valve No. 3 trap site. It would then cross back to the south side of E 1400 N Road, continue west approximately 0.4 mile across N 4100 East Road, and proceed west for another approximately 0.56 mile. The final segment would turn south for approximately 245 feet and terminate at the planned OES No. 1 injection well.
The route maps and digital files are provided for general route orientation and proximity review. They do not constitute a property survey or establish final construction boundaries.
Regional Project Location and Planned CO₂ Pipeline Route
This map shows the planned CO₂ pipeline route in relation to Gibson City, nearby communities, and the Ford and McLean County area.
Planned CO₂ Pipeline Route and Project Facilities
This map shows the planned route from the One Earth Energy facility near Gibson City to the planned sequestration facilities in Ford and McLean Counties.
One Earth Energy Facility and CO₂ Process Area
This map shows the One Earth Energy facility and adjacent One Earth Sequestration infrastructure, including the dehydration and compression facility and planned pipeline connection.
COUNTY PARCEL-MAPPING RESOURCES
Landowners may use the public county mapping resources below to locate their property by address or parcel identification number.
After locating the property, open the applicable OES route file in Google Earth and compare the property’s general location with the proposed route, 200-foot route corridor, or alternative route.
County parcel information and Google Earth imagery are provided for general reference. They do not constitute a survey or establish legal property boundaries or exact distances. Questions concerning a specific property may be submitted using the contact information in Section 8.
OPEN FORD COUNTY PARCEL VIEWER
https://ford-il.bhamaps.com/OPEN MCLEAN COUNTY GIS MAP VIEWER
https://experience.arcgis.com/experience/8ee41fdb613b42879a4b861dcf60f5c4/page/McGIS-Map-ViewerOPEN MCLEAN COUNTY PARCEL SEARCH
https://www.mcleancountyil.gov/parcelsearch
5. Pipeline Design, Safety, and Emergency Planning
One Earth Sequestration is developing the proposed CO₂ pipeline using documented engineering and safety criteria. Project planning addresses pipeline integrity, leak detection and monitoring, CO₂ dispersion modeling, risk assessment, emergency-response coordination, chemical-safety contingency planning, and community preparedness.
Several safety and emergency-planning materials are still under development. Public executive summaries will be posted after the underlying work is completed and the summaries receive the necessary engineering, security, and legal reviews.
GIS-Compatible Proposed Route File
This Google Earth file shows the currently proposed 8-inch CO₂ pipeline route from the One Earth Energy facility near Gibson City to the planned injection well, OES No. 1
Proposed 200-Foot Route Corridor
This Google Earth file shows an illustrative 200-foot-wide corridor centered on the currently proposed pipeline route, extending 100 feet on each side of the centerline. The proposed route and corridor may be refined during engineering and regulatory review
ALTERNATIVE PIPELINE ROUTE
OES evaluated an alternative pipeline alignment connecting the same project endpoints as the currently planned route: the CO₂ compression facility at the One Earth Energy site and the planned OES No. 1 injection well. The alternative follows a different alignment between those endpoints and is provided for comparison. It is not the route currently proposed for construction.
The KMZ files may be opened using Google Earth Pro on a computer or the Google Earth application on a compatible device. After opening a file, use the Places panel to turn the proposed route, 200-foot route corridor, and project-location layers on or off. Use the search function to locate an address or geographic area, then zoom in to compare its location with the proposed route or corridor.
These files are provided for general route-orientation and proximity review. Property boundaries shown by Google Earth or other third-party mapping services may not represent current surveyed parcel boundaries. For questions about a specific property, contact One Earth Sequestration using the contact information in Section 8.
-
The proposed system consists of an approximately 5.4-mile, 8-inch carbon dioxide pipeline connecting the existing carbon dioxide compression facility at the One Earth Energy site with the planned OES No. 1 injection well.
Pipeline design addresses route alignment and right-of-way requirements; pipe material, wall thickness, and pressure rating; required depth of cover; road, drainage, and utility crossings; automatic isolation and shutoff valves; pressure and temperature monitoring; overpressure protection; corrosion control and cathodic protection; instrumentation and communications; and operating and maintenance requirements.
The final design will incorporate the results of the project-specific hydraulic and surge analysis, dispersion modeling, risk assessment, and emergency-planning work and will comply with applicable federal and state pipeline-safety requirements.
-
The proposed approximately 5.4-mile, 8-inch carbon dioxide pipeline would be installed primarily below ground using conventional pipeline-construction methods. Anticipated activities include surveying and route staking, utility locating, preparation of approved work areas, limited clearing and grading where necessary, topsoil segregation, trenching, pipe delivery and installation, welding and inspection, protective-coating inspection, road and utility crossings, lowering the pipeline into the trench, backfilling, pressure testing, restoration of disturbed areas, and installation of cathodic-protection systems. Trenchless construction methods may be used at selected crossings where appropriate.
Major surface features would include the existing carbon dioxide compression facility and pipeline connection at the One Earth Energy site; the Mainline Valve No. 3 trap site, including isolation valves and associated piping, instrumentation, and control equipment; and the planned pipeline connection and surface equipment at OES No. 1. Limited pipeline markers and cathodic-protection test stations would also be installed along the route. Final construction methods and facility configurations may be refined during final engineering, permitting, and regulatory review.
-
A project-specific hydraulic and surge analysis has been completed for the proposed 8-inch carbon dioxide pipeline and one-well configuration. The analysis evaluated steady-state and transient operating conditions to support pipeline design, pressure control, and equipment protection. Public-facing information will be posted after the necessary engineering, security, and legal review.
-
The planned pipeline system will use pressure, temperature, and flow instrumentation, control-system alarms, operating procedures, and routine inspections to identify abnormal operating conditions.
If a potential release or other abnormal condition is identified, operators will evaluate the operating data and may initiate shutdown and isolate the affected pipeline segment using designated valves and response procedures. Final leak-detection, alarm, shutdown, and isolation provisions will be confirmed through detailed design, commissioning, risk assessment, dispersion modeling, and emergency-response planning.
-
One Earth Sequestration has initiated a project-specific risk-based assessment. A downloadable public executive summary will be posted here after the assessment is completed and approved for public release.
-
Project-specific CO₂ dispersion studies have been completed using consequence modeling and three-dimensional computational fluid dynamics modeling. The results are being evaluated to support pipeline safety, risk assessment, emergency planning, and the ICC application. A public-facing executive summary will be posted after the necessary engineering, security, legal, and publication-rights review.
-
One Earth Sequestration has initiated preparation of a chemical-safety contingency plan. A downloadable public executive summary will be posted here after the plan is completed and approved for public release.
-
One Earth Sequestration has prepared a draft Emergency Response Plan addressing leak detection, emergency shutdown and isolation, emergency contacts and notifications, incident command, public communication, protective actions, responder coordination, training, drills, and post-incident review. The plan is being updated for the current one-well project configuration and will incorporate relevant findings from the CO₂ dispersion modeling, risk-based assessment, and Chemical Safety Contingency Plan. Coordination with county emergency-management agencies and local emergency responders will continue as the plan is finalized.
-
Public-facing executive summaries of the pipeline design basis, hydraulic and surge analysis, and CO₂ dispersion modeling will be posted here after the necessary reviews are completed. Risk-assessment and chemical-safety-contingency-plan materials will be added after those efforts are completed and approved for public release.
6. Environmental and Cultural Resource Review
One Earth Sequestration is using environmental field studies, desktop reviews, mapping, and agency coordination to evaluate environmental and cultural resources along the proposed pipeline route. These reviews support project planning, permitting, and regulatory review.
Publicly available supporting materials will be added as the applicable reviews are completed.
-
Project planning has evaluated streams, drainage features, wetlands, groundwater, soils, floodplains, potentially contaminated sites, and other land and water resources along the current project corridor. Aquatic-resource field surveys have been completed for the areas evaluated, and the results have informed route planning, crossing methods, construction work areas, permitting, and restoration requirements.
A project-specific Water Impact Assessment has also been prepared to evaluate the additional groundwater demand associated with CCS operations. The assessment concludes that the additional demand is not expected to result in significant adverse impacts to the Mahomet Aquifer, nearby groundwater users, public water-supply systems, or surface-water resources.
Environmental protection measures include avoiding and minimizing impacts where practicable; using appropriate wetland, waterbody, road, and drainage-crossing methods; implementing stormwater, erosion, and sediment controls; conducting environmental inspections during construction; restoring disturbed areas; and monitoring revegetation and permit closeout. The project will comply with applicable federal, state, and local permits and agency requirements.
-
A project-specific Biological Assessment, supported by desktop review and field habitat surveys, has been completed and submitted to the U.S. Environmental Protection Agency. The consultant concluded that the proposed Project may affect, but is not likely to adversely affect, the listed and proposed species evaluated and identified no designated critical habitat within the assessed area. Agency review and consultation are ongoing. Public-facing materials will be posted after the necessary agency and legal review.
-
Phase I cultural resource fieldwork and a final survey report have been completed for the areas evaluated. The consultant concluded that the Project is unlikely to have an adverse effect on archaeological resources within the surveyed area and recommended no further archaeological investigation or avoidance. The report is being coordinated with the U.S. Environmental Protection Agency and the Illinois State Historic Preservation Office. Public-facing materials will be posted only after the necessary agency and legal review.
-
A draft Inadvertent Discovery Plan has been prepared to establish stop-work, protection, notification, evaluation, and consultation procedures if previously unidentified archaeological resources or potential human remains are encountered during construction. The plan will be updated for the final project configuration and coordinated with the responsible agencies, the Illinois State Historic Preservation Office, and consulting Tribes before construction begins.
-
One Earth Sequestration has completed a carbon-footprint assessment evaluating greenhouse-gas emissions associated with the manufacture, construction, operation, and maintenance of the proposed CO₂ pipeline and injection-well infrastructure. The assessment compares those emissions with the amount of CO₂ expected to be permanently sequestered.
The assessment is being updated to reflect the current one-well project configuration. A downloadable public version will be posted after the update is completed and approved for release.
-
Downloadable public versions of environmental and cultural-resource materials will be posted here when appropriate and after the necessary agency, technical, and legal reviews are complete.
7. ICC Application Materials and Project Updates
One Earth Sequestration has not yet filed an application with the Illinois Commerce Commission for a Certificate of Authority to construct and operate the proposed carbon dioxide pipeline. This section provides the current application status, anticipated construction timeline, and significant project updates. After the application is filed, the ICC docket number and publicly available application materials will also be posted here.
-
One Earth Sequestration is currently completing prefiling public outreach, engineering and environmental review, safety planning, and preparation of the ICC Certificate of Authority application. No application has been filed, and the proposed pipeline route has not been approved by the Illinois Commerce Commission.
Anticipated ICC application filing: Fall 2026
ICC docket number: Not yet assigned
After the application is filed, the ICC docket number, a direct link to the ICC e-Docket, publicly available application materials, and instructions for public participation will be posted here.
-
The project is currently in prefiling development, and specific construction dates have not been established. OES anticipates using a design-bid-build project-delivery approach. Under this approach, engineering and final design will be completed before construction work is bid and awarded to one or more qualified contractors. The project is expected to proceed through the following general phases. Construction will not begin unless and until OES receives the required ICC authorization and other applicable permits and approvals.
Phase 1 – Prefiling and Application Preparation — Current Phase
Complete engineering and environmental review, public outreach, required public meetings and notices, safety planning, and preparation of the ICC Certificate of Authority application.
Phase 2 – ICC Application and Regulatory Review
File the Certificate of Authority application and participate in the ICC review process. Application materials, the ICC docket number, and instructions for public participation will be posted after filing.
Phase 3 – Final Engineering and Preconstruction Preparation
Complete final engineering, surveying, utility identification, route staking, access planning, temporary-workspace preparation, procurement, construction contract award, and contractor mobilization.
Phase 4 – Site and Route Preparation
Prepare approved pipeline work areas and facility sites; establish required environmental and construction controls; segregate topsoil; and conduct limited clearing and grading where necessary.
Phase 5 – Pipeline and Facility Construction
Excavate the pipeline trench; install and inspect the pipeline; complete road, drainage, and utility crossings; install valves, instrumentation, and monitoring equipment; and complete the connections at the One Earth Energy facility and OES No. 1.
Phase 6 – Testing and Commissioning
Perform required pressure and integrity testing, verify monitoring and safety systems, complete final inspections, and commission the pipeline for operation.
Phase 7 – Restoration and Closeout
Backfill and restore construction areas; replace segregated topsoil; repair drainage features; stabilize and revegetate disturbed ground; and complete final cleanup and permit closeout activities.
This timeline is preliminary and phase-based. More specific schedule information will be posted as regulatory review, engineering, permitting, procurement, and construction planning advance. Physical construction will not begin unless and until the required ICC authorization and other applicable permits and approvals are obtained.
-
expansion and the One Earth Sequestration carbon capture and storage project. The analysis evaluates estimated construction and ongoing employment, employee earnings, economic output, and local property-tax benefits in Ford County, McLean County, and the State of Illinois. The report separately identifies the estimated economic impacts associated with the One Earth Sequestration project.
The complete report will be posted here after confirmation that it has been approved for public release.
-
After the ICC Certificate of Authority application is filed, the route exhibits included with the application will be posted here or made available through a direct link to the ICC e-Docket.
Current public route maps, GIS-compatible route files, the 200-foot route corridor, the alternative-route materials, and property-proximity instructions are available in Section 4 of this page.
-
August 2026
One Earth Sequestration launched this dedicated ICC Pipeline Information page. Prefiling public outreach, engineering and environmental review, safety planning, and preparation of the ICC Certificate of Authority application are ongoing. No application has been filed, and the proposed pipeline route has not been approved by the Illinois Commerce Commission.
Significant changes in project status, public-meeting schedules, ICC filings, and procedural milestones will be posted in this section within 14 days, as applicable.
August 26, 2026 — OES scheduled four prefiling public meetings. Meetings will be held at 10:30 a.m. and 5:30 p.m. on October 7, 2026, at the Countryside Campground Event Center in Gibson City and on October 15, 2026, at the McLean County Fairgrounds Mini-Expo Building in Bloomington. Complete meeting information is provided in Section 2.
8. Questions, Comments, and Project Contact
Members of the public may submit questions or comments regarding the proposed route, public meetings, environmental review, safety planning, or ICC application materials using the online form or the project contact information below. Members of the public may also sign up to receive email notifications of significant project updates.
After the ICC application is filed, this page will provide the docket number and instructions for submitting comments directly to the Illinois Commerce Commission. Comments submitted to One Earth Sequestration do not constitute a filing with the Commission.
-
Use the form below to submit a project question or comment. Questions regarding proposed construction activities may also be submitted through the form or any of the contact methods provided below and will be routed to the appropriate project representative.
Submitted questions and comments may be summarized or included in public-meeting records or regulatory filings and therefore may be subject to public disclosure. Please do not include confidential information or sensitive personal information.
-
To receive email notifications of significant project updates, provide your name and email address in the form below and select “Sign up for news and updates.”
-
General project questions and comments may be emailed to:
Webform@oneearthenergy.com
-
General project inquiries may be directed to One Earth Sequestration at 217-784-5321, extension 202.
-
One Earth Sequestration
Attn: ICC Pipeline Project
202 North Jordan Drive P.O. Box 526
Gibson City, Illinois 60936-0526 -
For media inquiries regarding One Earth Sequestration or the proposed carbon dioxide pipeline project, contact:
Rachel Torbert
PR Director, Rooster
217-519-2028
rachel@roosterstrategy.com
To submit a question or comment, complete the applicable fields below. To receive project updates, provide your name and email address and check “Sign up for news and updates.”
9. Regulatory Resources
The following official regulatory resources provide additional information regarding ICC review, Illinois carbon capture and sequestration requirements, emergency planning, pipeline safety, and federal Class VI permitting.
-
The Illinois Commerce Commission reviews applications for authority to construct and operate carbon dioxide pipelines in Illinois and is conducting a rulemaking concerning carbon dioxide pipeline requirements.
https://icc.illinois.gov/informal-processes/carbon-capture-initiative
-
This Illinois law establishes requirements for obtaining an ICC Certificate of Authority to construct and operate a carbon dioxide pipeline.
https://www.ilga.gov/Legislation/ILCS/Articles?ActID=3379&ChapterID=23
-
The SAFE CCS Act establishes additional Illinois requirements governing carbon capture, transportation, emergency planning, and geologic sequestration.
-
Illinois EPA is developing and administering the state permitting program established under the SAFE CCS Act.
https://epa.illinois.gov/about-us/rules-regs/illinois-safe-carbon-capture-sequestration-act.html
-
IEMA-OHS provides statewide emergency-management and preparedness information. This link will be updated if a dedicated page for carbon capture and sequestration safety materials becomes available.
-
The Pipeline and Hazardous Materials Safety Administration administers the federal pipeline-safety program and provides information concerning pipeline regulations, safety initiatives, and rulemaking.
-
The U.S. EPA Class VI program regulates wells used to inject carbon dioxide into deep geologic formations for long-term storage and protection of underground sources of drinking water.
https://www.epa.gov/uic/class-vi-wells-used-geologic-sequestration-carbon-dioxide
10. Page Information
Last updated: September 4, 2026
Applicant contact and accessibility assistance: Steve Kelly, One Earth Sequestration, 217-784-5321, extension 202, or skelly@oneearthenergy.com.
Website notice: This website is maintained by One Earth Sequestration. It is not an Illinois Commerce Commission website or docket.