Illinois CO₂ Pipeline Requirements
One Earth Sequestration is developing a carbon capture and storage project near Gibson City, Illinois. This page provides public information related to Illinois Commerce Commission review of the planned CO₂ pipeline, including project status, public meeting information, landowner notice information, planned route maps, safety planning, environmental and cultural resource review, and opportunities for public input.
1. Project Status at a Glance
-
Not yet filed.
-
Prefiling public outreach and preparation of the ICC application.
-
Ford County and McLean County, Illinois.
-
Dates, times, and locations will be posted when confirmed.
-
Available below for public review and download.
-
August 9, 2026.
2. Public Meetings
Public meetings will provide project information, an opportunity to ask questions, and an opportunity to submit comments before the ICC application is filed.
-
Date: To be announced
Time: To be announced
Location: To be announced
Materials: To be posted -
Date: To be announced
Time: To be announced
Location: To be announced
Materials: To be posted -
Date: To be announced
Time: To be announced
Location: To be announced
Materials: To be posted -
Date: To be announced
Time: To be announced
Location: To be announced
Materials: To be posted -
Each meeting location will be accessible to persons with disabilities. Information for requesting reasonable accommodations or interpreter assistance will be included in the applicable meeting notice.
-
Comments may be submitted at a public meeting or through the methods provided in the Questions and Comments section of this page.
3. Landowner Notices and Public-Meeting Documents
Public notices, meeting materials, and related documents will be posted in this section as they become available.
-
Posting date: To be announced
Document: To be posted -
Posting date: To be announced
Document: To be posted -
Posting date: To be announced
Document: To be posted -
Posting date: To be announced
Document: To be posted -
Posting date: To be announced
Materials: To be posted -
Posting date: To be announced
Document: To be posted -
Posting date: To be announced
Document: To be posted
4. Planned Route Maps
The following maps show the planned CO₂ pipeline route and related project facilities. Full-size versions will be available for public review and download.
Regional Project Location and Planned CO₂ Pipeline Route
This map shows the planned CO₂ pipeline route in relation to Gibson City, nearby communities, and the Ford and McLean County area.
Planned CO₂ Pipeline Route and Project Facilities
This map shows the planned route from the One Earth Energy facility near Gibson City to the planned sequestration facilities in Ford and McLean Counties.
One Earth Energy Facility and CO₂ Process Area
This map shows the One Earth Energy facility and adjacent One Earth Sequestration infrastructure, including the dehydration and compression facility and planned pipeline connection.
5. Pipeline Design, Safety, and Emergency Planning
One Earth Sequestration is developing the planned CO₂ pipeline using documented engineering and safety criteria. Project planning includes pipeline integrity, leak detection, CO₂ dispersion modeling, emergency response coordination, and community preparedness.
-
Project planning addresses route alignment, right-of-way, pipeline materials, road and utility crossings, automatic shutoff valves, corrosion control, instrumentation, and operations and maintenance.
-
The planned system will include instrumentation, monitoring, and operating procedures designed to identify and respond to abnormal operating conditions.
-
Site-specific CO₂ dispersion modeling, including three-dimensional computational fluid dynamics modeling, is being used to support pipeline safety evaluation, emergency planning, and the ICC application.
-
Emergency planning addresses emergency contacts, notification procedures, public communication, coordination with local emergency responders, training, and preparedness activities.
-
Public safety summaries and supporting materials will be posted as they become available.
6. Environmental and Cultural Resource Review
One Earth Sequestration is using environmental field studies, desktop reviews, mapping, and agency information to support project planning and regulatory review.
-
Project review includes land use, wetlands, streams, surface-water features, water resources, and construction best management practices.
-
Field studies, desktop review, mapping, and agency information are being used to evaluate threatened and endangered species and other protected-resource considerations.
-
Cultural resources review has been performed for the planned pipeline corridor and proposed project disturbance areas.
-
Project procedures address the appropriate response if cultural materials or human remains are unexpectedly encountered during construction.
-
Appropriate public environmental and cultural-resource materials will be posted as they become available.
7. ICC Application Materials and Project Updates
This section will be updated as ICC application materials, project updates, meeting materials, and public-comment responses become available.
-
Status: Not yet filed
Filing date: Not applicable
Public application materials: To be posted -
Date: To be announced
Document: To be posted -
Date: To be announced
Documents: To be posted -
Date: To be announced
Materials: To be posted -
Date: To be announced
Document: To be posted -
Updates will be posted here as they become available.
8. Questions, Comments, and Project Contact
Questions or comments may be submitted regarding the planned route, public meetings, environmental review, safety planning, or ICC application materials.
-
Use the public comment form provided below to submit a question or comment to One Earth Sequestration.
-
skelly@oneearthenergy.com
-
Office: 217-784-5321 Ext. 202
Cell: 217-781-4284 -
Steven Kelly, C.E.O.
One Earth Energy, LLC
202 N. Jordan Drive
Gibson City, Illinois 60936
9. Regulatory Resources
The following regulatory resources provide additional information regarding ICC review, Illinois carbon capture and sequestration requirements, pipeline safety, and federal Class VI permitting.
-
Information regarding ICC programs, proceedings, and carbon capture and sequestration rulemaking.
-
Illinois law governing applications for authority to construct and operate carbon dioxide pipelines.
https://www.ilga.gov/Legislation/ILCS/Articles?ActID=3379&ChapterID=23
-
Public Act 103-0651 establishes additional Illinois requirements for carbon capture, transportation, and sequestration projects.
https://www.ilga.gov/documents/legislation/publicacts/103/PDF/103-0651.pdf
-
Information about Illinois EPA implementation of the SAFE CCS Act and the state carbon sequestration permitting program.
https://epa.illinois.gov/about-us/rules-regs/illinois-safe-carbon-capture-sequestration-act.html
-
Federal information concerning carbon dioxide pipeline safety requirements and rulemaking.
-
Federal information about Class VI wells used for the permanent geologic sequestration of carbon dioxide.
https://www.epa.gov/uic/class-vi-wells-used-geologic-sequestration-carbon-dioxide
10. Page Information
Last updated: August 9, 2026
Accessibility assistance: For assistance accessing materials on this page, contact One Earth Energy at 217-784-5321.
This page will be updated as public-meeting information, notices, route materials, ICC filings, public-comment materials, and other project updates become available.